Pool and water tank waterproofing: from the concrete shell to the tiles

In a pool, unlike a bathroom, water presses on the walls constantly and from the inside. So the scheme has three layers: dense concrete and a watertight render with liquid glass, the cement-based waterproofing «Navitex» inside the shell, then tiles on an elastic adhesive and silicone grout. Outside, if the shell sits in the ground, a bitumen primer and mastic. Below: the stages and the quantities for a private pool and a utility tank.

How a pool differs from a bathroom

In a bathroom water lies on the surface and drains away; in a pool it presses on the walls all the time and enters every pore. So one elastic coat under the tiles is not enough: the waterproofing must be built into the concrete itself, with the coatings reinforcing it. A level drop of up to 1 cm a day is often plain evaporation; more is a leak.

Stage 1: concrete and render

The shell is poured in one go without joints, and construction joints (floor–wall) are sealed with a waterstop. The levelling render and screed are mixed with liquid glass, 5–10 % of the mixing water, so the layer becomes watertight. A 15 kg canister serves several hundred kilograms of mortar.

When pouring in cold weather an antifreeze admixture is added so the concrete gains strength without loss.

Stage 2: cement-based waterproofing inside

On the cured render (about 2–3 weeks), dampened with water as the pack instructs, «Navitex» is applied in two criss-cross coats; corners and pipe entries are taped beforehand. It enters the pores and densifies the concrete, and this is the layer that holds the pressure. An 18 kg pack covers roughly 10–12 m² in two coats, exact consumption on the pack.

Tiles go on an elastic water-resistant adhesive and are grouted with Bauer silicone grout: ordinary grout washes out of a pool in 1–2 seasons.

Typical mistakes

Bathroom coating in a pool. Ordinary grout that washes out. Tiles on render that has not dried. Pipe entries without tape. A fast first fill with no level check.

Stage 3: outside and utility tanks

If the shell is in the ground, groundwater presses from outside: the concrete is coated with the bitumen primer B. Superbit (0.3–0.5 kg per m²) and mastic, as for a foundation. For an irrigation or fire tank without tiles, two coats of «Navitex» are the finish.

For large and public pools that need a liner or a specialised system, ASB Engineering selects the materials and the crew after a site visit. Everything here is in stock in Tbilisi: order online, invoice right after the order; fast-delivery items arrive in Tbilisi on the day of the order if placed before 17:00 on a working day (otherwise the next working day), the rest in 2–3 business days, to the regions in 3–5 business days.

Related products

Need it installed? ASB Engineering does turnkey waterproofing — Our own crew: waterproofing of the pool, bathrooms, roofs, foundations and terraces in Tbilisi and the regions — asbengineering.ge

Write to us — we will work out the material for your sizes — Site chat or hello@asbshop.ge: tell us the area and the object, we reply in working hours

Frequently asked questions

Is bathroom waterproofing suitable for a pool?

No. The elastic coating under tiles is made for draining water, not constant pressure. A pool needs penetrating cement-based waterproofing in the concrete itself.

When can the pool be filled?

After the tiles and grout have fully dried, usually 7–14 days; the first fill slowly, watching the level.

An old pool leaks, what to do?

First a level test: more than 1 cm a day is a leak. Often it is enough to replace the grout with a silicone one and seal the pipe entries; if the shell leaks, the finish comes off and «Navitex» is applied anew.